Week 29 : 3/6/2023 - 3/13/2023

Updated: Mar 19, 2023

Rear Vent Visor Fan Adjustment

Following the findings last week involving the lack of clearance for the rear intake nozzles and potential risk of rain due to them hanging beneath the threshold of the vent visor, the fan position for windows 2 and 4 were reset. Fans were removed, holes were re-drilled, and previous holes were epoxied over using Clear Flex Glue to prevent rain from entering.

Shown below is the results of the fan reorientation, on the left is the nozzle location prior to flipping, nozzles location post flipping in the middle, and on the right the final location after re-drilling and moving.

Acceptance Test Procedure Writing

Given the number of tests required to fulfill our Engineering Requirements and the lack of specificity currently present in our current timeline, a Test Procedure was written which documents how each test which fulfills our requirements will be performed with the test setup and any special notes made in advance prior to the start of testing. A .PDF file has been posted on the Website in the Design Project dropdown menu. A snippet of the Test Setup is shown below.



9 views0 comments

Recent Posts

See All

Comments


bottom of page